The Auckland Material Recovery Facility (MRF) was a joint-venture project between Auckland Council and Visy Recycling (NZ) Ltd. The MRF now handles recycling collected from Council’s 265,000 households – catering for over 770,000 people or approximately 20 per cent of New Zealand’s population. 

It is one of the southern hemisphere’s most technologically advanced MRF facilities. This flagship facility is on 3.6 ha of the former Galway Street closed landfill in Onehunga, Auckland. This construction location presented aggressive and potentially unstable ground conditions and was actively producing methane gas. In addition, it is adjacent to the Manukau Harbour – a sensitive, ecologically valuable water body. 

It has received praise from local and central government for its design and delivery.

Services

Consents

  • Scoping of likely resource consents, building consents and engineering approvals required
  • Management of the resource consents application programme
  • Assessment of Environmental Effects (AEE), including preparation of the AEE report
  • Preparation and lodgement of resource consent applications
  • Technical input for resource consent (land use) and building consent applications
  • Presentations at consent hearings
  • Consent condition compliance observation and
  • reporting during construction
  • Preparation of a site-specific Environmental
  • Management Plan for operation of the MRF to satisfy consent conditions
  • Post-construction and pre-occupation compliance monitoring and reporting

Industrial Structures

  • Scoping of likely resource consents, building consents and engineering approvals
  • Site investigation (contamination and geotechnical) of a portion of the closed landfill
  • Preparing a factual site report for inclusion in the RFT
  • Preparing a base plan (existing services, topography etc.) of a portion of the closed landfill
  • Assisting council in outlining requirements and expected outcomes for invited tenderers
  • Consents, design and supervision of the enabling works (including the relocation and encapsulation of the historical contaminated materials stockpile) before successful tenderer taking possession of the site
  • Design of foundations and ground improvement works
  • Design of landfill gas protection measures for the main building and associated structures
  • Construction observation related to the management of contaminated materials, site preparation, piling installation and testing, ground improvement works monitoring, and installation of landfill gas protection measures for the main building and associated structures.

Air quality

  • Scoping of likely resource consents, building consents and engineering approvals
  • Design of landfill gas protection measures for the main building and associated structures
  • Construction observation for installation of landfill gas protection measures for the main building and associated structures
  • Post-construction and pre-occupation compliance monitoring and reporting
  • Preparation of a site-specific Environmental Management Plan for the MRF operation to satisfy consent conditions.

Contaminated Land

  • Scoping of likely resource consents, building consents and engineering approvals
  • Collating all historical investigation data for the closed landfill site and preparing a report for inclusion in the RFT
  • Site investigation of a portion of the closed landfill and preparing a factual report for inclusion in the RFT
  • Consenting, design and supervision of the site enabling works (including relocation and encapsulation of the historical contaminated materials stockpile) before successful tenderer taking possession of the site
  • Design of landfill gas protection measures
  • Construction observation
  • Preparation of site validation reports required by consents

Client

  • Visy Recycling (NZ) Ltd
  • Auckland Council

Year

  • 2020

Explore More Projects

Stonnington Waste Transfer Station

Stonnington Waste Transfer Station

Melbourne Regional Landfill

Melbourne Regional Landfill

Knox Transfer Station Odour and Dust Monitoring

Knox Transfer Station Odour and Dust Monitoring

previous arrow
next arrow

How can we help?

Get in touch with a Tonkin + Taylor representative today. Our friendly and knowledgeable team make it easy to find the right solution to suit your specific needs.

Get In Touch